In which of the following scenarios does the project manager implement documentation well? Select all that apply.
a. The key stakeholder determines they want to add a feature to the product in development. The project manager includes this update in the project charter and communicates it to the team.
b. Because the project manager doesn't have all the project's details, they ask a current team member to onboard the new team member.
c. The project manager shares the project timeline on a cloud-based document sharing program.
d. A stakeholder talks with two different team members and receives conflicting information on a vendor. They cannot find information about the vendor in the shared document drive.