The project team spent $10,000 to prototype a new technology. The new technology will not meet the project requirements. The team estimates it will take $5,000 to prototype a different technology. The team is doing a cost-benefit analysis of running the second prototype. What cost should the team use?
Group of answer choices
$5,000
$10,000
$15,000
$7,500