The project has a CPI = 1.05 and has spent $1,500,000 (USD) to date. The project manager is preparing for a sponsor and key stakeholder status update. The project manager has determined the remaining cost estimates to complete the project are inaccurate. What should the project manager forecast for the project spend?
Group of answer choices
Calculate and report TCPI
Calculate and report EAC based on past performance
Calculate and report the ETC
Calculate and report EAC after re-estimating