Using the PERT formula, calculate the time (t) for each
activity.
QUESTION 4 4.1 The following table represents data of a project you are working on: Most Optimistic Most likely Activity Predecessor Most Pessimistic Time in days 4 H 8 24 10 11 12 24 14 25 16 27 15 3