Early in the project's planning phase, the project team determined that the cost to install the server would be 15,000. This is a high-level estimate, and the team thinks it may cost up to 10,000 more. What kind of estimate is this?
a) Rough Order of Magnitude (ROM)
b) Definitive
c) Budgetary
d) Parametric