1. Which of the following scenarios best describes a Classic structure?
1. Imagine you are managing an important project at a company that requires all orders to go through its shipping department. However, your project is on a tight schedule, and the shipping department has a
backlog of orders. You decide to meet with your direct manager to ask for approval to place the order through a third-party
vendor. Ultimately, your direct manager has to meet with a vice president to get final
approval?

2. Imagine you work alongside a small group of project managers. One of your current projects shares team
members with another, ongoing
project. To make sure you hit your next milestone, you want your team
members to work only on your project for
the next two weeks. You decide to meet with your team to discuss
your proposal?

3. Imagine you work at a small marketing agency, and you have just begun a new project. All of the company's
graphic designers work in
the Art department and report to the Art Director. However, two of those graphic
designers have been assigned to
your project, so they will also report to you while working on the project?