Answer:
Total cost to get the ready to use: 132,100
Explanation:
Equipment cost: 120,000 x (1 - 1%) = 118,800
shipping cost: 2,000
special wiring connections 10,000
installation cost 1,300
Total cost to get the ready to use: 132,100
All cost incurred to get the equipment ready to use and produce must be included in the equipment cost.