Answer:
The beginning of the extraction activities is 14.7 million.
Explanation:
Please find the detailed answer as follows:
Present Value of Cash Flows Expected From the Project/Asset Retirement Obligation at the Beginning = (.60*10 + .40*30)*PVIF(7%,3 Years) = (.60*10 + .40*30)*.81630 = 14.7 million .