You are working with your project team to schedule activities for your construction project. You have the carpet installation activity may begin. The relationship between the painting activity and carpet instalionacvity can atwity lo be can best be described as_____________.a. Lag.b. Lead.c. Finish-to-start.d. Start-to-finish

Respuesta :

Answer:

c.

Explanation:

Based on the information provided with regards to the situation at hand it can be said that the relationship between these two is a Finish-To-Start relationship. This refers to having to finish something in order to be able to start the next part. Which is exactly the case in this scenario, since the painting activity must be finished first and only then can the carpet installation activity can begin.