Answer:
D. Size of the home.
Explanation:
The most appropriate cost allocation base would be to trace major activity driver in the building of homes. Since the homes ranges from 2500 to 8000 sq feet. The appropriate way to allocate costs would be on the basis of per square feet that takes in to account the size of the house. Kemp would be better of by tracing per sq feet costs as they allow a more closer version to activity based costing.
Hope that helps.