______________--relationships between activities. For example, one activity may not be able to start until another has finished, or perhaps one activity is dependent on another activity starting before it can finish. We'll cover several types of dependencies next.

Respuesta :

Answer:

FINISH TO START

Explanation:

Dependencies are types of relationships between preceding & succeeding activities .

4 Types : Finish to Start, Start to Start, Finish to Finish, Start to Finish

One activity (succeeding) can start only of the another (preceding) has finished is: FINISH TO START . Eg - Food can be cooked only if all the ingredients have been bought.

Start to Start- Preceding Activity must start before Succeeding Activity can be started ; Finish to Finish- Preceding Activity must be finished before Succeeding Activity can be finished ; Start to Finish- Preceding Activity must be started before Succeeding Activity can be finished.