"Different from aggregate planning, Master Production Schedule (MPS) shows detailed disaggregation of the aggregate production plan, listing the exact end items to be produced by a specific period" is TRUE.
Option: A
Explanation:
A schedule for the manufacturing of specific items, such as growth, staffing, inventory, etc. in each time period. It is usually related to production where the schedule determines when and how much will be required for each product, thus understood as a master production schedule (MPS).
A promotional practice which carries out a cumulative strategy for the manufacturing process, 6 to 18 months in advance, to give the leadership an idea as to what amount of materials and other supplies are to be obtained and when, so that the organization's total operating costs are kept to a minimum over that timeframe, the phenomenon is termed as aggregate planning.