Stones Corporation uses a predetermined overhead rate based on machine-hours to apply overhead to the manufacturing process. Last year, Stones incurred manufacturing overhead costs totaling $450,000 and used 100,000 machine-hours. This year, Stones estimated manufacturing overhead to be $550,000 and expected to incur 110,000 machine-hours. Stones actually incurred $575,000 of manufacturing overhead and incurred 120,000 machine-hours this year. What is the manufacturing overhead application rate?
A. $5.00 per machine-hour
B. $4.79 per machine-hour
C. $4.50 per machine-hour
D. $5.50 per machine-hour

Respuesta :

Answer:

A. $5.00 per machine-hour

Explanation:

The computation of the manufacturing overhead application rate is shown below:

= Estimated manufacturing overhead ÷ expected machine-hours incurred

= $550,000 ÷ 110,000 machine hours

= $5.00 per machine hour

In order to determine the  manufacturing overhead application rate, basically we divided the estimated manufacturing overhead by the expected machine hours