Answer:
A. $5.00 per machine-hour
Explanation:
The computation of the manufacturing overhead application rate is shown below:
= Estimated manufacturing overhead ÷ expected machine-hours incurred
= $550,000 ÷ 110,000 machine hours
= $5.00 per machine hour
In order to determine the manufacturing overhead application rate, basically we divided the estimated manufacturing overhead by the expected machine hours