Answer:
$1000
Explanation:
Total factory rent is $2500 for 5000 sq ft. The basis for assigning the rent cost to different activities will be on the basis of factory area used.
Factory area used by different activities is as follows,
1. Machining 500 sq ft
2. Preparation & Setup 2000 sq ft
3. Quality Control 2000 sq ft
4. Finishing 500 sq ft
So, The cost that will be assigned to the Preparation and setup cost will be
$2500 * 2000/5000 = $1000