Answer:
$21.65
Explanation:
The computation of the standard cost is shown below:
= Material cost + labor cost + factory overhead cost
where,
Material cost = 3 ÷ 4 × $5 per yard
= $3.75
Labor cost = 2 hours × $5.75 = $11.5
And, the factory overhead cost is
= $3.20 × 2 hours
= $6.4
So, the standard cost is
= $3.75 + $11.5 + $6.4
= $21.65