Answer:
The correct answer is option e
e. Zero to $5,000
Explanation:
Net Present Value (NPV) : This is one of the techniques available to evaluate the feasibility of an investment project. The NPV of a project is the difference between the present value of the cash inflows and the cash outflows of the project discounted at the required rate of return
PV of cash inflows
= $15,600 × (1.15)^(-1) + ( $15,600× 1.15^(-2) + ($28,900 × 1.15^(-3) ($15,200 × 1.15^(-4)
=53,053.92
NPV =53,053.92-48,100
NPV =4,953.927