Answer:
Optimal mix
Reno = 615 units
Tahoe = 0 units
Explanation:
Whenever a company is faced with a limiting factor i.e a resource in short supply, the company should allocate the resource to the product with he highest contribution per unit of the scare resource
Product Cont/unit painting hr /unit cont/hr Ranking
Reno $120 4 30 Ist
Tahoe $78 3 26 2nd
The company should use all of its limited 2,460 painting hours to produce the two products as follows:
Reno
= 2460/4
= 615 units of Reno
This is so as long as Billings Company can produce and sell as many units of Reno as it can produce.
Optimal mix
Reno = 615 units
Tahoe = 0 units