Answer:
A. Take $1 million now.
Explanation:
A. If we take $1 million now the present value of the money is $1 million.
B. If we choose to take $1.2 million paid out over 3 years then present value will at 10% will be;
$300,000 + $300,000 / 1.2 + $300,000/ 1.44 + $300,000 / 1.728
$300,000 + $250,000 + $208,000+ $173,611 = $931,944
The present value of option B is less than present value of option A. We should select option A and take $1 million now.