Quad Enterprises is considering a new three-year expansion project that requires an initial fixed asset investment of $2.3 million. The fixed asset falls into the three-year MACRS class (MACRS schedule). The project is estimated to generate $1,720,000 in annual sales, with costs of $628,000. The project requires an initial investment in net working capital of $270,000, and the fixed asset will have a market value of $210,000 at the end of the project.
a. If the tax rate is 22 percent, what is the project’s Year 0 net cash flow? Year 1? Year 2? Year 3? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and enter your answers in dollars, not millions of dollars, rounded to two decimal places, e.g., 1,234,567.89.)
b. If the required return is 10 percent, what is the project's NPV? (Do not round intermediate calculations and enter your answer in dollars, not millions of dollars, rounded to two decimal places, e.g., 1,234,567.89.)

Respuesta :

Answer:

a)

MACRS 3 year depreciation schedule

33.33% x $2,300,000 = $766,590

44.45% x $2,300,000 = $1,022,350

14.81% x $2,300,000 = $340,630

carrying value at end of year 3 = $170,430

net after tax cash flow from salvage value = $210,000 - [($210,000 - $170,430) x 22%] = $201,294.60

cash flows:

year 0 = -$2,300,000 - $270,000 = -$2,570,000

year 1 = [($1,720,000 - $628,000 - $766,590) x 0.78] + $766,590 = $1,020,410

year 2 = [($1,720,000 - $628,000 - $1,022,350) x 0.78] + $1,022,350 = $1,076,677

year 3 = [($1,720,000 - $628,000 - $340,630) x 0.78] + $340,630 + $201,294.60 + $270,000 = $1,397,993

b)

NPV = $297,794, and IRR = 16.12%