contestada

An activity variance is due to the difference between the level of activity used in the flexible budget and the actual level of activity.

a. True
b. False

Respuesta :

Zviko

Answer:

a. True

Explanation:

The Activity variance is based on the difference in actual level of activity used in flexible budget and the level of activity accounted in the planning or master budget