It takes 4 people 10 hours to plaster a section of a building. How long will it take 8 people to
do the same job working at the same rate?

Respuesta :

Answer:

5 hours

Step-by-step explanation:

sgo

Answer:

5 hours because you have double the people which means it would take half the time :)

Hope this Helps! :)

Have any questions? Ask below in the comments and I will try my best to answer.

-SGO