Respuesta :
Answer:
Explanation:
The Earned Value Analysis for each term can be computed as follows:
Term Acronym Formula Value
Budget At Completion BAC =1000×500 500,000
Planned Value PV =400×500 200,000
Earned Value EV =500000×0.45 225,000
Actual Cost AC 250,000
Cost Variance CV [tex]=EV - AC[/tex] -25,000
Schedule Variance SV [tex]=EV - PV[/tex] 25,000
Cost Performance Index CPI [tex]=EV / AC[/tex] 0.9
Schedule Performance Index SPI [tex]=EV / PV[/tex] 1.125
Estimate At Completion EAC [tex]=BAC / CPI[/tex] 555,556
Estimate To Complete ETC [tex]=EAC - AC[/tex] 305,556
Variance At Completion VAC [tex]=BAC - EAC[/tex] -55,556