Answer:
32 seconds
Explanation:
According to the scenario, computation of the given data are as follows,
Average observed time = 20 seconds
so, if the employee worked at 20% faster pace, then
Performance rating = 1.20
So, Normal time = 20 seconds × 1.20 = 24 seconds
Here, Allowance = 25%
Now, we can calculate the standard time by using following formula,
Standard time = Normal time ÷ ( 1 - Allowance)
By putting the value, we get
Standard time = 24 seconds ÷ ( 1 - 0.25)
= 24 ÷ 0.75
= 32 seconds