Answer:
The correct statement is:
a. There would be no accumulation of work-in-process inventory.
Explanation:
Daily demand of product A = 20 units
Working time per day = 12 hours
Time to process a unit on Resource X = 30 minutes
Time to process a unit on Resource Y = 15 minutes
Total units that can be processed on Resource X per day = 24 (12/0.5)
Total units that can be processed on Resource Y per day = 48 (12/0.25)
Since Resource X feeds Resource Y and both resources are scheduled to work 12 hours per day, there will no accumulation of work-in-process (from Resource X) because Resource Y uses half the time of Resource X.