20 men can do a piece of work in 24 days. After working for few days, 3 men are added and the work was finished 3 days earlier. After how many days if 4 men are added?​

Respuesta :

Answer: 17 and a half

Step-by-step explanation:

M    D    W

20  24  480

20   21  420

24   17 and a half  420

= 17 and a half