Answer:
Direct labor cost= $396,000
Explanation:
Giving the following information:
Production:
May, 13,500 units
June, 16,500 units
July, 21,500 units.
Each unit requires 2 labor hours at $12 per hour.
First, we need to calculate the number of hours required for June:
Number of direct labor hours= 16,500*2= 33,000 hours
Now, the direct labor cost:
Direct labor cost= 33,000*12= $396,000