Answer:
1779 veh/h
Explanation:
Given :
Peak hour factor, PHF = 0.84
Heavy vehicle adjustment factor, [tex]$F_{HV}$[/tex] = 0.847
Analysis flow rate, [tex]v_p[/tex] = 1250 pc/h/ln
We know that,
Analysis flow rate, [tex]$v_p=\frac{v}{(PHF)(N)(F_g)(F_{HV})}$[/tex]
Here, v = peak hour volume
[tex]$F_g$[/tex] = grade adjustment factor which is 0.99 for rolling terrain.
> 1200 pc/h/ln
[tex]$v_p=\frac{v}{(PHF)(N)(F_g)(F_{HV})}$[/tex]
[tex]$1250=\frac{v}{(0.84)(2)(1)(0.847)}$[/tex]
v = 1779 veh/h
Therefore, the peak hour volume, v = 1779 veh/h