What is the minimum cost of crashing the following project that roger solano manages at slippery rock university by 4​ days?.

Respuesta :

Answer:

The minimum cost of crashing the project that Roger Solano manages at Slippery Rock University by 4 days is $1100

Explanation:

The critical path of the project = Longest path of the project = CE

= 4 + 8

= 12 days

Other Paths = AD

= 6 + 5

= 11 days

In order to reduce project time by 4 days , we need to crash

C by 1 day,

E by 3 days

A by 1 day

D by 2 days

so as to have the total project duration be 8 days

Cost of crashing = Crashing cost of A, C, D, and E

= (1000 - 900) + (600 - 500) + (1200 - 900) + (1600-1000)

= 100 + 100 + 300 + 600

= $1100