The contracting officer received a claim in the amount of $178 000 on june 11 2011. on august 18, 2011, she issued a final decision. what should have she requested when she sent her final decision?

Respuesta :

She should have requested a certified claim when she sent her final decision

This is further explained below.

what should have she requested when she sent her final decision?

Generally, A certified claim was something the contracting officer probably would have asked for.

Within sixty days of the receipt of a certified claim for more than one hundred thousand dollars, a contracting officer is obligated to either (A)issue a final decision; or (B)notify the contractor of the time period within which a final decision will be issued. One of these two options must be followed.

In conclusion, When she should have handed in her final decision, she should have asked for a certified claim instead.

Read more about the certified claim

https://brainly.com/question/8422118

#SPJ4