which of the following is an assumption made by the critical path method (cpm)? a. the activity time estimates are accurate and stable. b. activities are dependent on each other, without clearly defined start and finish times. c. activities are interrupted many times before completion. d. the project network defines a tentative work sequence that can be changed anytime during the project.

Respuesta :

Yormex

The following is an assumption made by the critical path method (cpm):

  • a. the activity time estimates are accurate and stable.

What is a Critical Path Method?

The Critical Path Method (CPM) is a means where one determines activities that are important for project completion and identify scheduling flexibilities. A critical path in project management is the longest series of activities that must be completed on time purposely to complete the entire project.

Therefore, the assumption made by the critical path Method as to do with estimation of time which is accurate and stable for the execution of a project.

learn more about Critical Path Method: https://brainly.com/question/15091786