Respuesta :
The total cost of finishing the work is $39,420.
How is total cost calculated ?
- Total Cost: Average Variable Cost Per Unit * Quantity of Produced Units + Total Fixed Cost + Total Fixed Cost
- When someone uses the term "whole cost" in the context of finance, she may be referring to a number of different things. She may be referring to the expenses associated with operating a business, the expenses covered by a person's personal budget, or even the expenses associated with a proposal (like a stock market investment.)
- Fortunately, your fundamental methodology will be the same regardless of what you're calculating the "total cost" for. Just add the fixed expenses (the minimal expenditures necessary to operate) to the variable costs (the costs that rise and fall at your discretion).
- The total cost of direct materials and labour as well as the total cost of manufacturing overhead can be added together to get the total cost of the product. A business can set an appropriate sales price for the finished item with the aid of information like the cost of production per unit.
Given data :
The computation of the total cost of ending work in process is shown below:
Equivalent cost per unit
Material = $301,600 ÷ 5,200 units = $58 per unit
Conversion = $405,500 ÷ 5,000 units = $81.10 per unit
Now ending work in process is
= 400 units × $58 + 200 units × $81.10
= $23,200 + $16,220
= $39,420
Hence, the total cost of ending work in process is $39,420
Learn more about total cost calculated refer to :
https://brainly.com/question/25109150
#SPJ4