Performance Task no. 1
We can plan!
DIRECTION: With your
partner, choose an existing
business that produces a
product, and create a sample
Gantt chart based on its
process.

Respuesta :

Answer:

Sure, let's say we choose a pizza restaurant as our existing business. Here's a sample Gantt chart based on the process of making and delivering a pizza:

| Task | Duration (days) | Start Date | End Date |

|---------------------|-----------------|------------|------------|

| Concept Development | 3 | 2024-02-25 | 2024-02-28 |

| Recipe Creation | 2 | 2024-02-29 | 2024-03-01 |

| Ingredient Procurement | 4 | 2024-03-02 | 2024-03-05 |

| Kitchen Preparation | 1 | 2024-03-06 | 2024-03-06 |

| Dough Making | 2 | 2024-03-07 | 2024-03-08 |

| Toppings Preparation | 1 | 2024-03-09 | 2024-03-09 |

| Assembly | 1 | 2024-03-10 | 2024-03-10 |

| Baking | 1 | 2024-03-11 | 2024-03-11 |

| Quality Check | 1 | 2024-03-12 | 2024-03-12 |

| Packaging | 1 | 2024-03-13 | 2024-03-13 |

| Delivery | 1 | 2024-03-14 | 2024-03-14 |

| Feedback Collection| 2 | 2024-03-15 | 2024-03-16 |

This Gantt chart outlines the various tasks involved in the pizza-making process, along with their durations and corresponding start and end dates. It provides a visual representation of the workflow, helping in planning and managing the activities efficiently.