When developing the milestone schedule for the project charter it is helpful to identify relatively few milestones and key deliverables.
a. True
b. False?

Respuesta :

cici66
This anwser is false because it does not give enough informations

Answer:

The correct answer is letter "A": True.

Explanation:

In project management, a milestone schedule lists the various activities necessary to achieve certain objectives. This approach is helpful for project managers to assess and evaluate when delays exist. In the milestone schedule, the executives mark the completion of certain activities resulting from the establishment of a formal end to the business.

In such a scenario, it is convenient if managers set a moderate number of milestones or project deliverables so they can keep the correct track of the progress of the work.